Huntington Hills Lake Restoration

Huntington Hills Lake Project Dates – Update 12/17/2009

July 2004 – Lake Drained at the Direction of SC DHEC
November 8, 2005 – Woolpert Report on Lake Huntington presented to City
June 25, 2007 – Stormwater Utility Ordinance
August 13, 2007 –- Stormwater Management Ordinance
January 28, 2008 – Council Approval of Schnabel Engineering
May 5, 2008 – Meeting with Home Owners on Lake Ownership
May 10, 2008 – Sufficient Property Owner Approvals to Begin Design
June 5, 2008 – Schnabel Engineering Meeting Onsite
June 24, 2008 – Tidewater Environmental Begins Wetland and Army Corps Permitting
July 22, 2008 – F&S to Begin Surveying
September 10, 2008 – Drilling Subcontractor onsite
September 25, 2008 – Council Drop in - Labyrinth Weir Design
November 14, 2008 – Army Corp Permit - Formally submitted
December 15, 2008 – Army Corp Permit Approved
December 17, 2008 – SCDOT approval to use bridge for access
January, 2009 – DHEC 401 permit
January 7, 2009 – DHEC Stormwater NOI Exemption with DHEC Dam Permit
January 12, 2009 – Advertise Excavation Phase 1
February 11, 2009 – Bid Opening Excavation Phase 1
February 16, 2009 – Easements with Downstream Property Owner
February 23, 2009 – Seek Council Approval of Excavation Phase 1 Contractor
February 23, 2009 – Labyrinth Weir Specifications and Drawings Complete (Schnabel Engineering)
March 15, 2009 – Advertise Labyrinth Dam Construction Phase 2 (City of Anderson)
March 16, 2009 – Notice to Proceed - Excavation Phase 1
April 15, 2009 – Bid Opening - Labyrinth Weir Construction Phase 2
May 9, 2009 – State Revolving Fund - End of Thirty Day Public Notice
May 18, 2009 – Council Approval of Labyrinth Construction Phase 2
May 21, 2009 – State Revolving Fund Loan Commitment Letter (DHEC)
June 4, 2009 – Notice to Award - Labyrinth Construction Phase 2
June 8, 2009 – First Reading of CWSRF Loan
June 22, 2009 – Second and Third Reading of CWSRF
June 29, 2009 – Notice to Proceed - Labyrinth Construction Phase 2
July 13, 2009 Complete – (100 Days) Excavation Phase 1
September 11, 2009 – First Concrete Placement

Anticipated Milestones

January 29, 2010 – Complete (215 Days or ~7 Months) Labyrinth Phase 2
April 2010 – Ribbon Cutting